Civic Centre Resource Library Update – March 20

This week at the Civic Centre Resource Library, structural steel erection is ongoing and appears to be almost complete. Work is being done at the main entrance canopy at the southeast corner. Connection welding has commenced. Distribution of Open Web Steel Joists (OWSJ) across the beam continues. Metal decking on the first floor roofs has started at the collaboration spaces.

CCRL

Steel being erected at the main entrance canopy.

OWSJ installation is ongoing.

OWSJ installation is ongoing.

Vertical framing around roof edge is ongoing.

Vertical framing around roof edge continues.

Metal decking commenced west of the reading garden.

Metal decking commenced west of the reading garden.

Steel connections are ongoing.

Steel connections continue to be installed.

 

 