Civic Centre Resource Library – June 5

Things are moving very quickly at the Civic Centre Resource Library. As of this week the masonry walls are complete at both levels. Walls have been built on the ground floor office area. Duct work and electrical wires continue to be installed.

1

View of the south elevation.

2

Masonry work is complete in the children's area.

3

Second floor mezzanine curbs have been poured for equipment.

4

Duct work and electrical installation are ongoing.

5

Stair B masonry is complete.

6

View of interactive family area and storage room.

 