Pleasant Ridge Update – Sept. 5

Bookmark and Share

As of this week, the window frames have been delivered on site, the roofing membrane installation is in progress, the window openings are being tarped and more are still happening. Here is a quick photo update.

photo 1photo 2photo 3

Pleasant Ridge Library Update – Aug. 27

Bookmark and Share

As of this week, all masonry work has been completed. Roof insulation and HVAC roof top units are being installed. Installation for the curtain wall frame and the directional boarding for electric secondary service feed are in progress.

Masonry

Masonry work has been completed.

Roff

Roofing work is in progress.

 

Pleasant Ridge Library Update – Aug. 20

Bookmark and Share

If you pass by Pleasant Ridge Library this week, you will see that a lot of masonry work has been done already. Work on the air barrier and the roofing has begun!

Aug. 20

Brick cladding installed on the west elevation.

Aug. 20

Brick cladding installed on the south elevation.

Aug. 20

Masonry work being done on the north wall.

Aug. 20

Earth spoils have been removed.

Aug. 20

Roofing work begun.

 

Pleasant Ridge Update – Aug. 13

Bookmark and Share

Construction continues at Pleasant Ridge this week and things are moving quickly.

Photo 1

Brick cladding units for masonry arrived on site.

Photo 2

Workers working on masonry scaffolding on the west side of the building.

Photo 3

Workers doing masonry work on the south wall.

Photo 4

Air vapour has been installed at the glazed wall.

Photo 5

The interior partition work has been completed.

Photo 6

The interior mechanical and electrical rough-in work continues.

Pleasant Ridge Library Update – August 1

Bookmark and Share
Pleasant Ridge Library

Parapet rough carpentry completed

Pleasant ridge library

Mechanical and electrical work at Link

Pleasant ridge library

Exterior wall substrate

Pleasant ridge library

Mechanical plumbing rough‐in

Pleasant ridge library

Duct work installation

Pleasant ridge library

Roof deck at high roof to be installed

Pleasant Ridge Library Update – July 25

Bookmark and Share
Pleasant ridge library

Duct work installation

Pleasant ridge library

Electrical rough in work along library west wall

Pleasant ridge library

Sprinkler installation connection from existing facility

Pleasant ridge library

Steel stud partition installation

Pleasant ridge library

Duct work installation

Pleasant ridge library

Mock up of air barrier‐ window & foundation drip edge

Pleasant Ridge Library Update – July 21

Bookmark and Share

 

Major activities including duct work installation, electrical rough-in, and the installation of sprinkler piping and exterior cladding substrate continue.

Pleasant_ridge_library

Structural stud and cladding installation

Pleasant_Ridge_Library

Sprinkler main installation in existing community centre

Pleasant_Ridge_Library

Sprinkler installation at high ceiling section

Pleasant_Ridge_Library

HVAC duct work installation

Pleasant_Ridge_Library

Electrical wiring installation at entrance

Pleasant_Ridge_Library

Exterior wall substrate installation

Pleasant Ridge Library Update – July 9

Bookmark and Share

Construction on the Pleasant Ridge Library continues to progress smoothly. The installation of exterior cladding substrate has started. Work continues on the installation of the duct work, electrical rough-in, sprinkler piping and radiant floor lines.

Pleasant Ridge Library

HVAC ductwork distribution installation

Pleasant Ridge Library

Electrical rough-in at garden entry doorway

Pleasant Ridge Library

Exterior wall steel stud installation

Pleasant Ridge Library

Sprinkler main line installation

Pleasant Ridge Library

Radiant floor heating line installation

Pleasant Ridge Library

Exterior wall substrate installation

Pleasant Ridge Library Update – June 30

Bookmark and Share

The site signage is up at Pleasant Ridge Library. The installation for the duct work, electric rough-in, sprinkler main are in progress. The roof top units have already been installed.

june 27

Site signage is up

june27

Installing the duct work

june 27

Installing the electric rough-in

june 27

Installing the sprinkler main

june 27

Opening the roof for roof top units

june27

Roof top units installed

Pleasant Ridge Library Update – June 17

Bookmark and Share

The parameter wall structure, drywall steel installation are progressing at Pleasant Ridge Library. The roof curb material arrived for installation and drywall steel studs are being installed.

June 17

Parameter wall structure in progress

June 17

Parameter wall base track at the reading garden entrance being built

June 17

Curb and parapet material on site

June 17

Drywall steel studs installation in progress

June 17

Drywall installation in progress