Civic Centre Resource Library – April 3

Bookmark and Share

As of this week, the primary structural steel is almost complete. Installation of secondary steel such as trim edges is ongoing. Connection welding continues. Metal decking over the first floor is in place and has started on the second floor. Mechanical and electrical rough-in has begun. Installation of rain water leaders at the collaboration space is underway. Conduit runs are being installed at the maker space and music room areas.

Apr.3

Steel work is ongoing.

april 2

Decking work has commenced at second floor.

april3

Grading is ongoing in preparation for slab on grade.

april3

Electrical rough-in commenced above ground at maker space & music room.

april3

Roof joist connections are ongoing.

 

 

Civic Centre Resource Library Update – March 20

Bookmark and Share

This week at the Civic Centre Resource Library, structural steel erection is ongoing and appears to be almost complete. Work is being done at the main entrance canopy at the southeast corner. Connection welding has commenced. Distribution of Open Web Steel Joists (OWSJ) across the beam continues. Metal decking on the first floor roofs has started at the collaboration spaces.

CCRL

Steel being erected at the main entrance canopy.

OWSJ installation is ongoing.

OWSJ installation is ongoing.

Vertical framing around roof edge is ongoing.

Vertical framing around roof edge continues.

Metal decking commenced west of the reading garden.

Metal decking commenced west of the reading garden.

Steel connections are ongoing.

Steel connections continue to be installed.

 

 

Civic Centre Resource Library Update – March 6

Bookmark and Share

Things are moving quickly at the Civic Centre Resource Library. Structural steel erection continues. Approximately 95% of the steel is installed. Connections have been tied down and bolted together. Open Web Steel Joists (OWSJ) are being distributed across the beams. Secondary steel framing around the roof edge is being installed.

roof

Secondary steel framing at the roof is being installed.

OWSJ

The Open Web Steel Joists is being installed.

CCRL

Elevator pit is protected.

CCRL

East elevation steel is in place.

CCRL

Steel work continues at the southeast main entrance.

 

Civic Centre Resource Library Update – Feb. 20

Bookmark and Share

This week at the Civic Centre Resource Library site, steel work continues to progress despite the cold weather. Check out some photos below.

CCRL1

View looking west into the building.

CCRL2

The future children's area.

CCRL

The future adult collections area.

CCRL

Steel is in place for the second floor outdoor reading garden.

 

 

 

Civic Centre Library Update – Feb. 6

Bookmark and Share

Construction of the Civic Centre Resource Library continues to move along this week. Check out a few photo updates below.

CCRLFeb.

View of the east elevation.

CCRL2

Corridor along the south elevation. Washrooms and proposed cafe to be on the left.

CCRL3

View from the Teen Zone into the Reading Garden.

CCRL4

Awaiting steel for electrical, IT rooms and offices at the east elevation.

CCRL

Columns and trusses at the literacy stations are in place.

CCRL

Framing of the library continues.

CCRL

Framing of thebuilding continues.

 

 

Civic Centre Resource Library Update – Jan. 23

Bookmark and Share

This week has been a great week at the Civic Centre Resource Library as workers continue to construct the frames of the building.  Take a look at the site from different views and imagine how stunning the library will look once construction finishes.

CCRL

View of the east elevation.

CCRL

View of the west elevation.

CCRL

View of the south elevation.

CCRL

View of the southwest corner.

CCRL

Study hall view looking north.

CCRL

Collaboration space has taken form.

CCRL

Connections bolted in place.

CCRL

Second delivery of steel has arrived.

Civic Centre Resource Library Update – Jan. 9

Bookmark and Share

Construction of the Civic Centre Resource Library continues to move quickly in the New Year. Take a look at the steel frames being put up right now.

CCRLCCRLCCRLCCRL

Civic Centre Resource Library Update – Dec. 12

Bookmark and Share

The holidays are approaching, but work at the Civic Centre Resource Library is not slowing down. Concrete work for the foundations has been completed; piers and cloumn bases have been covered with straw, plastic and gravel for weather and moisture protection; reading garden bench concrete has cured and formwork has been removed and more.  See below for some great photo updates!

CCRL

Concrete work for the foundations has been completed. Final installation for insulation was taking place at the northeast corner.

CCRL

Piers & column bases have been covered with straw, plastic and gravel for weather and moisture protection.

CCRL

Reading garden bench concrete has cured and formwork has been removed.

CCRL

Underground services appear to be complete and stubbed up above grade for further connections.

CCRL

Elevator pit has been fenced off.

CCRL

North perimeter foundations view.

CCRL

Grading has commenced on the proposed interior around the reading garden.

CCRL

Gravel is on site for slab on grade preparation.

Civic Centre Resource Library – Nov. 19 update

Bookmark and Share

There’s lots happening at the Civic Centre Resource Library construction site this week! Check out some new photo updates below.

CCRL

Formwork continues along the east wall at the north corner.

CCRL

Elevator pit has been poured and formwork has been removed.

CCRL

Reading garden perimeter foundations appear to be complete and backfilled.

CCRL

Interior trenching for underground services has commenced.

CCRL

Stair B foundation is complete.

CCRL

Foundation waterproofing and insulation is ongoing.

Civic Centre Resource Library Update – Nov. 12

Bookmark and Share

Things are progressing at the Civic Centre Resource Library this week. Workers continue to work on the formwork and the foundations. The waterproofing of the foundations has commenced. The rebar installation has been completed. Forms are ready for concrete on the right and the concrete pour has been completed on the left side.

CCRL

Formwork and foundations are ongoing.

CCRL

Waterproofing of the foundations has commenced.

CCRL

Rebar installation has been completed.

CCRL

Piers are completed and formwork has been removed.

CCRL

Forms are ready for concrete on the right and concrete pour is complete on the left.

CCRL

General view of the site.