Vellore Village Library – Getting ready to open on August 11!

Bookmark and Share

Things are shaping up quickly at Vellore Village Library! Books have been delivered to the library today and staff are busy setting everything up. The library will be open to the public starting on August 11 at 10 a.m., make sure you stop by to check it out!


      

 

Vellore Village Library: July 27 Update

Bookmark and Share

A new sign and new furniture for the library!

Library name on the building

The library now has its name on the building.

Soft chairs arrived

Soft, comfy chairs have arrived.

Installed balcony glass

Balcony glass has been installed.

Renovations have begun at Bathurst Clark Resource Library

Bookmark and Share

Contractor, Massive Devon has begun renovation work at Bathurst Clark Resource Library (BCRL).

New children's area

View of the new children’s area from BCRL’s main entrance.

Children's area-view from main hall

View of the new children’s area from BCRL’s main hall.

Children's area, looking east.

The children’s area, looking east.

Children's area looking west

The children’s area, looking west.

Renovated women's washroom

Women’s washroom being renovated.

Vellore Village Library: July 23 Update

Bookmark and Share

Library construction continues to progress nicely.

Shelves ready to be stacked with books

Shelves ready to be stacked with books.

Tile flooring on balcony

Tile flooring placed on outdoor balcony.

Finishing the ceiling facade

Finishing the ceiling façade.

Vellore Village Library: July 13 Update

Bookmark and Share

Deliveries of new furniture and shelving have arrived!

New furniture arrived.

New furniture for Vellore Village Library.

Shelving delivery has arrived.

Shelving has been delivered to library.

Shelving in the library

Shelving inside the Vellore Village Library ready for installation.

Installation of shelves has begun.

Shelving installation has begun.

Installation of shelving

Shelving installation

Shelving installation at VVL.

The shelving installation at Vellore Village Library continues…

Bathurst Clark Resource Library ready for renovations

Bookmark and Share

Bathurst Clark Resource Library (BCRL) has been closed since Friday, June 29. In one short week, thanks to the BCRL staff and the moving company, important items were stored, furniture was taken apart, books were packed away and shelving was dismantled. A (mostly) empty building is now ready for the contractors, Massive Devon, to begin their work.

Furniture ready for the movers

Furniture ready for the movers.

BCRL facing north

The view inside Bathurst Clark Resource Library facing north.

Empty shelves

Empty shelving  ready to be taken apart.

BCRL facing southeast

Facing southeast – the shelves and furniture are now removed.

Library cleared of materials. Facing south.

Facing south – the library has been cleared of all materials and resources.

Vellore Village Library: July 6 Update

Bookmark and Share

The construction of the new library adjacent to Vellore Village Community Centre continues to steadily progress.

Library entrance

Entrance to Vellore Village Library.

Nature-inspired decor

Nature-inspired decor.

Display shelving installation

Installation of display shelving.

Bench seating in children's area

Bench seating installed in the children’s area.

Installation of customer service desk

Customer Service desk being installed.

Counter-height seating overlooking skate park

Counter-height seating overlooking the skate park.