Pleasant Ridge Library is opening on December 20 at 10 a.m. We invite everyone to come and see this beautiful new library and check out all the great services and programs the library offers. See you there!
Pleasant Ridge Library Opens Dec. 20
![Bookmark and Share](https://s7.addthis.com/static/btn/v2/lg-share-en.gif)
There’s lots happening at the Civic Centre Resource Library construction site this week! Check out some new photo updates below.
Things are progressing at the Civic Centre Resource Library this week. Workers continue to work on the formwork and the foundations. The waterproofing of the foundations has commenced. The rebar installation has been completed. Forms are ready for concrete on the right and the concrete pour has been completed on the left side.
Things are progressing at Kleinburg Library. The second floor duct work is being finished, the east side windows have been installed, and the retainer wall for the new basement entrance has also been completed.
Construction work on the Civic Centre Resource Library began in September. Excavation of the site is now completed and the site has been elevated and leveled to the level of the street.
Workers have now finished the footing installation, and the installation of foundation wall forms and backfilling of the building envelope continues.
Here are a few photo updates of the construction site.
Things are moving along at Kleinburg Library. Here’s a quick photo update of what’s happening.
Here is a quick photo update of what’s happening at Pleasant Ridge Library this week.
The renovation project at Kleinburg Library is experiencing some delays and the library is now expected to re-open on Monday, December 8 at 1 p.m.
The book drop will continue to be closed during this time. You may return your library materials to any branch of Vaughan Public Libraries or renew them online.
You can also deactivate your holds online or pick them up at Pierre Berton Resource Library. If you require assistance deactivating your holds, please contact the Service Desk. We apologize for any inconvenience.
This week at Pleasant Ridge Library, the spray foam insulation have been applied to the walls, the electrical distribution panel has been installed. Workers installed the glass windows on the south and north side of the building. The framing of the exterior soffit continues.