Dufferin Clark Library Unveils Revitalized Study and Computer Areas

Bookmark and Share

Dufferin Clark Library recently revitalized its study and computer areas thanks to a generous donation of new tables made by the two local plants of Wholesome Harvest Baking Ltd., Rivermede and Viceroy, as part of their Good Neighbor Project which aims to generate a positive change in the surrounding community. Wholesome Harvest Baking Ltd. is a division of Grupo Bimbo, a Mexican multinational bakery product manufacturing company.

On Dec. 10, the library unveiled the new areas to more than 100 students from the Charlton and Glen Shields Public Schools followed by an interactive musical named ROCKgarden Party. The musical was a hit with the children and taught them a great lesson about the importance of protecting the environment.

From L to R: Wholesome Harvest Baking Ltd. staff: Debbie Sher, HR Advisor; Eryn Whitehead, Human Relations Manager; Same Yehia, Viceroy Plant Manager; Rob Ferraioli, VP of Supply Chain; Sharon McNamara, Rivermede Plant Manager; Robyn Thompson, Senior Director of HR; VPL Staff: Margie Singleton, CEO; Aleksandra Dowiat-Vine, Director of Growth & Communications; Sandy Vanderwerff, Director of Finance & Community Spaces; Lisa McDonough, Director of Customer Experience; Middle: Bimbo Mascot

From L to R: Wholesome Harvest Baking Ltd. staff: Debbie Sher, HR Advisor; Eryn Whitehead, Human Relations Manager; Sharon McNamara, Rivermede Plant Manager; Rob Ferraioli, VP of Supply Chain; ; Same Yehia, Viceroy Plant Manager; Robyn Thompson, Senior Director of HR; VPL Staff: Margie Singleton, CEO; Aleksandra Dowiat-Vine, Director of Growth & Communications; Sandy Vanderwerff, Director of Finance & Community Spaces; Lisa McDonough, Director of Customer Experience; Middle: Bimbo Mascot

Students enjoying the ROCKgarden Party musical.

Students with Skater Dude and Earth Angel.

New study area.

The revitalized study area.

The revitalized computer area.

 

 

 

Civic Centre Resource Library – Dec. 9

Bookmark and Share

This week at the Civic Centre Resource Library, workers continue to install composite panels on the south side. Framing work is still ongoing at the main entrance. Glazing installation continues to move along around the exterior perimeter. Electrical work is underway for connections to the elevator. Gas feed to the building is in place and heaters are on site to be installed. In addition, trees for the courtyard have been planted.

Concrete work is complete at the west elevation.

Drywall installation is in progress at the adult collections area.

Front entrance frame work is ongoing.

Trees have been planted in the courtyard.

Civic Centre Resource Library – Nov. 30

Bookmark and Share

Things are moving quickly at the Civic Centre Resource Library. Here is an update on what is happening at the construction site.

  • Exterior insulation installation is taking place around the north, west and south elevations.
  • Workers continue to install paneling on the south side.
  • Framing work is still ongoing at the main entrance at the south side.
  • Glazing installation continues around the exterior perimeter at the east elevation.
  • Hardscaping activities continue around the building.
  • Sidewalk continues to be poured around the perimeter as well as the pads at the main entrance.
  • Drywall installation continues throughout the first and second floor.
1

Concrete work is ongoing around the perimeter.

2

Hardscaping work is progressing at the south side.

3

Drywall work is almost complete.

4

Lounge area and study hall space in progress.

 

Civic Centre Resource Library – Nov. 12

Bookmark and Share

Things are moving quickly at the Civic Centre Library. Here is a quick update on what is happening as of this week.

  • Exterior insulation installation is complete at the south side of the building.
  • Framing and welding at the main entrance is ongoing.
  • Glazing installation continues around the exterior perimeter at the east elevation.
  • Composite panel installation is progressing at the north side and around the Reading Garden.
  • Sidewalks are 50% poured at the north side and curb work is progressing at the east and north sides.
  • Interior steel stud work has progressed in all areas.
  • Drywall installation continues throughout the first and second floors.
Floor pLan

Floor Plan - 1st floor.

Floor Plan 2

Floor Plan - 2nd floor.

View of east elevation.

Sidewalk is 50% poured at the east elevation.

Hardscape work has progressed at the east side.

Steel welding and aluminum welding at the main entrance is ongoing.

Glazing installation is complete at the Reading Garden with the exception of the exits.

View of the second floor patio. Roof work is complete and finish work is to be scheduled.

Vaughan Public Library Board announces the official name of the new resource library

Bookmark and Share

The Vaughan Public Library Board is pleased to announce VPL’s third resource library will be officially named the Civic Centre Resource Library. The name was selected from an extensive list of suggestions received from hundreds of Vaughan citizens, through a survey, and additional names of historical significance amassed with input from City of Vaughan Archives staff. VPL thanks everyone who provided their valuable input in naming this library.

Construction of the Civic Centre Resource Library is progressing well. As of this week, the exterior insulation installation is ongoing at the south side of the building perimeter with roxul insulation. Glazing installation continues around the exterior perimeter. Another shipment of glazing has been received and installation along the south and east walls are to commence. Hardscaping along the south, west and north sides are ongoing. Mechanical and electrical rough-ins are complete. Connections of exhaust fans and fixture rough-ins are underway. Interior steel stud work has progressed in all areas. Drywall installation continues throughout the first and second floor.

View of the south elevation.

Framing and insulation work is ongoing at the market place.

View of the main entrance at the south.

Walls at the Digital Media Lab are taking form.

Walls at the Digital Media Lab are taking form.

View of the 2nd floor patio.

 

Civic Centre Resource Library – Oct. 9

Bookmark and Share

Glazing installation continues around the exterior perimeter. The north and west elevations as well as the reading garden are approximately 90% closed in. Hardscaping activities along the south, west and north continues.  Grading is almost complete along the north. Mechanical and electrical rough-ins are complete. Interior steel stud work has progressed in all areas. Drywall installation is underway at the mezzanine and second floor areas.

glazing

Glazing installation is almost complete at the reading garden.

market place

View of the Market Place with second floor balcony above.

Music Room

Music Room walls are taking form.

Stairs

Drywall mudding and taping has commenced at stair B.

Program room

Insulation and boarding is progressing at the program rooms and kitchenette.

offices

2nd floor administration area is starting to take form.

Civic Centre Resource Library – Sept. 25

Bookmark and Share

Things are really shaping up at the Civic Centre Resource Library this week. The exterior sheathing installation continues at the south side of the building. Glazing installation is ongoing around the exterior perimeter as well. Fritted glazing installation along the north and west are also being installed. Check out some photo updates.

View of south elevation. Hardscaping and sheathing are ongoing.

Framing work is ongoing at the main entrance.

Interior insulation and framing are ongoing at the music and control rooms.

Frit glazing installation is ongoing.

Staircase construction is ongoing.

 

 

 

Civic Centre Resource Library – Sept. 18

Bookmark and Share

This week at the Civic Centre Resource Library, exterior sheathing installation continues to progress around the building perimeter and work is ongoing at the south side. Glazing installation has commenced and panels are being installed around the reading garden as well as the north elevation. Hardscaping activities started along the south with the drilling and installation of sonotubes for piers.

1

Exterior commenced at the south elevation.

2

Glazing installation commenced at the north elevation.

3

Hardscaping work has commenced. Workers are drilling piles to install sonotubes.

4

Interior insulation has commenced at the adult collection.

6

Glazing installation at the Reading Garden is ongoing.

 

 

Civic Centre Resource Library – Sept. 3

Bookmark and Share

Construction continues to move quickly at the Civic Centre Resource Library. Check out some quick photo updates below.

1

Coordination is ongoing between installation of services.

Steel framing is in place for Maker Space and Teen Area.

View of Stair B.

View of northeast corner.

View of Reading Garden.

 

Civic Centre Library – Aug. 10

Bookmark and Share

Things are really shaping up at the Civic Centre Resource Library! Check out some photo updates from last week.

2

View of east elevation.

2

Main entrance area - view of elevator.

3

View of the adult collection area.

5

Mechanical and electrical work continues at the mezzanine.

6

Partition wall framing is ongoing and almost complete at the second level.