Pleasant Ridge Library Update – Aug. 20

Bookmark and Share

If you pass by Pleasant Ridge Library this week, you will see that a lot of masonry work has been done already. Work on the air barrier and the roofing has begun!

Aug. 20

Brick cladding installed on the west elevation.

Aug. 20

Brick cladding installed on the south elevation.

Aug. 20

Masonry work being done on the north wall.

Aug. 20

Earth spoils have been removed.

Aug. 20

Roofing work begun.

 

Pleasant Ridge Update – Aug. 13

Bookmark and Share

Construction continues at Pleasant Ridge this week and things are moving quickly.

Photo 1

Brick cladding units for masonry arrived on site.

Photo 2

Workers working on masonry scaffolding on the west side of the building.

Photo 3

Workers doing masonry work on the south wall.

Photo 4

Air vapour has been installed at the glazed wall.

Photo 5

The interior partition work has been completed.

Photo 6

The interior mechanical and electrical rough-in work continues.

Pleasant Ridge Library Update – August 1

Bookmark and Share
Pleasant Ridge Library

Parapet rough carpentry completed

Pleasant ridge library

Mechanical and electrical work at Link

Pleasant ridge library

Exterior wall substrate

Pleasant ridge library

Mechanical plumbing rough‐in

Pleasant ridge library

Duct work installation

Pleasant ridge library

Roof deck at high roof to be installed

Civic Centre Library Update – July 31

Bookmark and Share

The fence is now up surrounding the site where the new resource library will be built in preparation for the construction phase of the project.

 

 

Pleasant Ridge Library Update – July 25

Bookmark and Share
Pleasant ridge library

Duct work installation

Pleasant ridge library

Electrical rough in work along library west wall

Pleasant ridge library

Sprinkler installation connection from existing facility

Pleasant ridge library

Steel stud partition installation

Pleasant ridge library

Duct work installation

Pleasant ridge library

Mock up of air barrier‐ window & foundation drip edge

Kleinburg Library Closed For Renovations August 1 – November 8

Bookmark and Share

 

Kleinburg Library, located at 10341 Islington Avenue North, will be closed for renovations starting Friday, August 1 to Saturday, November 8 at 1 p.m.

Kleinburg Library

Renovations to the Library will be done both inside and outside of the building.

Interior Renovations:

  • Adding two large windows to the front of the library on the main level increasing the visibility to see both into and out of the library
  • Creating a large new window on the south wall of the library’s upper level
  • Levelling the floor on the upper level and putting down new carpet
  • Adding a new railing for the stairway
  • Installing new lighting and HVAC throughout
  • Renovating the staff workroom
  • Upgrading electrical and data requirements

Exterior Renovations:

  • Replacing the existing fire and emergency stair structure on the north side
  • Creating a reading garden on the south side of the library
  • Completing the cement pathway from front of library to new rear entrance
  • Replacing all existing windows
  • Improving exterior lighting
  • Replacing existing wood/aluminum siding
  • Repairing and replacing roof
  • Removing existing roof ladder
  • Adding new entrance to lower floor of library from exterior on east side
  • Removing existing exterior stairs and structure to lower level from front of library

Customers can deactivate their holds online or pick them up at Pierre Berton Resource Library at 4921 Rutherford Road. If you require assistance deactivating your holds, please contact the Service Desk. The book drop will also be closed during this time. You may return your library materials to any branch of Vaughan Public Libraries or renew them online at www.vaughanpl.info. We apologize for any inconvenience.

Pleasant Ridge Library Update – July 21

Bookmark and Share

 

Major activities including duct work installation, electrical rough-in, and the installation of sprinkler piping and exterior cladding substrate continue.

Pleasant_ridge_library

Structural stud and cladding installation

Pleasant_Ridge_Library

Sprinkler main installation in existing community centre

Pleasant_Ridge_Library

Sprinkler installation at high ceiling section

Pleasant_Ridge_Library

HVAC duct work installation

Pleasant_Ridge_Library

Electrical wiring installation at entrance

Pleasant_Ridge_Library

Exterior wall substrate installation

Pleasant Ridge Library Update – July 9

Bookmark and Share

Construction on the Pleasant Ridge Library continues to progress smoothly. The installation of exterior cladding substrate has started. Work continues on the installation of the duct work, electrical rough-in, sprinkler piping and radiant floor lines.

Pleasant Ridge Library

HVAC ductwork distribution installation

Pleasant Ridge Library

Electrical rough-in at garden entry doorway

Pleasant Ridge Library

Exterior wall steel stud installation

Pleasant Ridge Library

Sprinkler main line installation

Pleasant Ridge Library

Radiant floor heating line installation

Pleasant Ridge Library

Exterior wall substrate installation

Pleasant Ridge Library Update – June 30

Bookmark and Share

The site signage is up at Pleasant Ridge Library. The installation for the duct work, electric rough-in, sprinkler main are in progress. The roof top units have already been installed.

june 27

Site signage is up

june27

Installing the duct work

june 27

Installing the electric rough-in

june 27

Installing the sprinkler main

june 27

Opening the roof for roof top units

june27

Roof top units installed

Groundbreaking Ceremony for the New Resource Library

Bookmark and Share

VAUGHAN, ON –  Vaughan Public Libraries (VPL) announced yesterday that Aquicon Construction Co. Ltd. has been selected to build the third resource library in the City of Vaughan, which will be located at 2191 Major Mackenzie Drive. The Vaughan Public Library Board, Mayor and Members of Council attended a groundbreaking ceremony for the new library to celebrate the start of the construction phase of the building project. The library, designed by ZAS Architects is anticipated to open in 2015.

 “This is another great moment for the Civic Centre Resource Library building project. We are very pleased to have Aquicon Construction on board to help us make the new resource library a reality.” said Michael McKenzie, Chair of Vaughan Public Library Board. “This new library is both a significant and valuable addition to both Vaughan Public Libraries and the City of Vaughan. Like all of VPL’s branches, it will provide a welcoming destination that educates, excites and empowers our community,” added McKenzie.

“Designing the new library is an exciting yet difficult task. To ensure the library meets the needs of our community, we adopted a collaborative design approach by incorporating suggestions from members of the community gathered from surveys, focus groups and community meetings conducted over the past few years.” said Margie Singleton, CEO, Vaughan Public Libraries. “I am delighted to say that the new library will indeed meet the many needs of our diverse community”.

The exterior of the library building is spectacular yet uniquely designed. It features a transparent look created by:

  • The use of a collection of concave semi-mirrored surface
  • A library façade that reflects its surroundings and patrons while suggesting a layered set of interior spaces
  • Peaked roofline extending above the perimeter of “heritage landscape”
  • Scalloped façades that address the scale of both driver and pedestrian with a gradient of transparent to reflective glass and metal panels

The interior of the library is futuristic yet welcoming and features the following:

  • Ample natural lighting and high ceilings
  • Good acoustic design
  • Flexible, adaptable and easily convertible spaces
  • Specific areas for teens, children, quite reading, serious studying and an collaboration
  • Exciting marketplace full of inspiring and enticing library materials
  • A Digital Media Lab
  • An internal courtyard that is open to the elements

In addition, the library is designed to be a green building which complies with the City of Vaughan’s Green Building Policy. It will also be an accessible facility that offers accessible shelving and technologies to accommodate individuals with special needs.

Groundbreaking

(From left to right): VPL Board Trustees Steve Kerwin, Isabella Ferrara, Grace Locilento, Suri Rosen, Regional Councillor and VPL Board Trustee Michael Di Biase, Deputy Mayor, Regional Councillor and VPL Board Trustee Gino Rosati, President of Aquicon Construction Co. Ltd Daniel Aquino, Mayor Maurizio Bevilacqua, VPL Board Chair Michael McKenzie, VPL CEO Margie Singleton, Ward 1 Councillor and VPL Board Trustee Marilyn Iafrate, Regional Councillor Deb Schulte, Ward 4 Councillor Sandra Yeung Racco, Ward 3 Councillor and VPL Board Trustee Rosanna DeFrancesca, Architect of ZAS Architect Inc. Dieter Janssen and VPL Board Trustee Lorraine de Boer attending the Civic Centre Resource Library groundbreaking ceremony on June 26.

Groundbreaking

(From L to R): President of Aquicon Construction Co. Ltd. Daniel Aquino, Mayor Maurizio Bevilacqua, VPL Board Chair Michael McKenzie, VPL CEO Margie Singleton and Dieter Janssen of ZAS Architects Inc.

Groundbreaking

(From L to R): Emilio Fullone and Robert Aquino of Aquicon Construction Co. Ltd., VPL Director of Planning and Communications Terri Watman and Dieter Janssen of ZAS Architects Inc.

groundbreaking

Executive Team from VPL (From L to R): Aleksandra Dowiat Vine, Terri Watman, Margie Singleton, Sandy VanderWerff and Lisa McDonough

groundbreaking

Master of Ceremonies – VPL Board Chair Michael McKenzie

groundbreaking

Mayor Maurizio Bevilacqua

groundbreaking

Ward 1 Councillor and VPL Board Trustee Marilyn Iafrate